Handover at RtB is the exception, not the standard case: usually we build on to commissioning and keep or sell the finished plant. Where a handover does take place at RtB, the development risks have been worked through at that point: land, grid connection agreement, planning consent and detailed design are in place, certification is prepared, and the financial model rests on evidenced assumptions.
Handing over earlier is possible as well — as co-development from secured land, or as a forward purchase from the grid connection grant. On large schemes a buyer may also take only the project rights or the secured site. Entering earlier means buying cheaper and carrying part of the development risk. That is a choice, not a fallback.
At the far end the axis is our normal case: through construction, into commissioning and into operation — on our own books or for buyers. Which stage is the right one for a handover is decided by the project and the partner, not by a standard sequence.